PT-2026-099 · dossier edition · 24 July 2026

PlatformTrace

Enterprise platform change across Ireland and the United Kingdom.

cloud and infrastructure migration · Completed data-centre compute migration · High confidence

Carne Group completes data-centre compute migration to Microsoft Azure

Carne Group moved all compute resources supporting its products from a local third-party data centre to Microsoft Azure in about six months.

Organisation
Carne Group
Predecessor
Third-party local data centre hosting product-specific virtual-machine compute resources
Destination
Microsoft Azure landing zones using Azure Site Recovery, Azure Backup and Terraform
Workload
All compute resources supporting Carne Group products
Stage
Completed data-centre compute migration
Retirement status
The named product-supporting compute estate exited the local data centre; storage, network, SaaS and unrelated external dependencies are not fully enumerated.
Confidence
High
Next trigger
A dated cutover statement, formal facility exit confirmation or later IaaS-to-PaaS completion milestone.
Evidence boundary: The source explicitly supports all compute resources supporting Carne products. It does not prove retirement of every storage, network, SaaS or third-party dependency.

Programme context

Carne Group depended on a third-party local data centre for virtual-machine provisioning, backup and operational changes. Regulatory guidance enabling cloud adoption and the company's need for greater resilience and autonomy created the migration boundary.

Why this matters: The source states a completed data-centre compute move, identifies the Azure implementation pattern and separates the finished migration from later cloud-native modernisation.

Migration timeline

Date or stageMilestoneWhat changedEvidence status
Prior operating stateSource conditionProduct compute ran in a local third-party data centre with provider-dependent provisioning and backup operations.Source-stated predecessor
About six monthsMigration executionAzure Site Recovery replicated virtual machines into product-specific Azure landing zones.Source-stated duration
Prior yearCompletion milestoneAll product-supporting compute resources had moved to Azure before the March 2026 story.Source-stated completed state
13 Mar 2026Evidence milestoneMicrosoft published the current customer account.Dated primary evidence

Workload migration matrix

WorkloadPredecessorDestinationStatus by 24 Jul 2026
Product-supporting virtual-machine computeThird-party local data centreMicrosoft Azure landing zonesCompleted
Backup, recovery and resilience controlsProvider-mediated backup and restorationAzure Backup, Azure Site Recovery, Azure Policy and Azure MonitorOperational
Post-migration application modernisationIaaS-hosted virtual machines and legacy middlewareAzure App Service, Azure SQL, Azure Service Bus and other PaaS servicesOngoing; not part of the completed migration claim

Implementation and architecture

  • Terraform-based landing zones separated each product environment.
  • Azure Site Recovery replicated compute and data states before a controlled cutover.
  • An application gateway already pointed to on-premises endpoints, allowing the team to switch backend targets after migration.
  • Azure Backup, Azure Policy and Azure Monitor were added to the post-migration operating model.
  • Later migration from virtual machines to cloud-native services remains a separate programme.

Known unknowns and contradictions

  • The exact final cutover date.
  • The full list of storage, network and external dependencies that remained outside the compute migration.
  • Whether the third-party facility contract or every associated service was formally terminated.
  • The completion date for later IaaS-to-PaaS modernisation.

No missing fact is inferred to convert the bounded compute migration into a whole-estate retirement claim.

PlatformTrace analysis

The strongest evidence is the explicit statement that all compute resources supporting Carne products moved from the local data centre to Azure. The source also clearly separates that finished lift-and-shift from later modernisation of databases, Windows services, messaging and traffic management.

PlatformTrace therefore records a completed data-centre compute migration with residual non-compute scope preserved as unknown.

Evidence ledger

  1. Microsoft customer story, 13 March 2026

    Direct Carne Group statements identify the source data centre, all-compute scope, Azure target, six-month duration, implementation pattern and ongoing post-migration modernisation.

Approval: Issue #47 standing-authority publication queue.

Corrections and updates

24 July 2026 — Initial Verified long-format dossier published after complete five-lane intake, central filter reconciliation and fresh primary-source reopening. Later milestones will be appended rather than silently replacing this state.