- Organisation
- Virginia DBHDS
- Predecessor
- VITA-hosted SQL Server EDW
- Successor
- Snowflake on AWS
- Implementation partner
- Deloitte
- Programme cost
- $11.08 million
- Production scope
- 40 Community Service Boards
- Retirement status
- Not explicitly confirmed
- Confidence
- High
Programme context
DBHDS launched the Enterprise Data Warehouse programme to replace an existing VITA-hosted warehouse maintained by the agency. Official planning material describes the old environment as the existing SQL Server enterprise data warehouse and identifies the new destination as a data platform hosted by VITA in AWS. Technical and governance sources name Snowflake as the analytical core.
Programme objective: consolidate behavioural-health data from Community Service Boards and other systems, improve timeliness, refactor reporting and implement a master patient index capable of recognising one individual across multiple services.
Programme timeline
| Date | Milestone | Meaning | Status |
|---|---|---|---|
| 3 Apr 2023 | Project start | Start recorded in the FY24–26 IT strategic plan. | Confirmed |
| 28 Feb 2025 | Original planned end | Original planning horizon before later implementation and closeout movement. | Superseded plan |
| Jul 2024 | Deloitte contract begins | Implementation contract for the replacement data platform. | Confirmed |
| Aug 2024 | Development environments | AWS and Snowflake development access was being enabled. | Confirmed |
| Mar–May 2025 | Production migrations | CSB production readiness and go-lives were active across multiple EHR vendors. | Confirmed |
| Dec 2025 | Final release implemented | The project team reported delivery of the final release. | Confirmed |
| Feb 2026 | Planned closeout | Administrative closeout target after the final release. | Planned |
| May 2026 | Portfolio marked complete | VITA moved the project into its completed-project portfolio. | Confirmed |
Workload and source-system matrix
| Component | Role in programme | Status | Evidence boundary |
|---|---|---|---|
| Community Service Boards | Primary production data providers; 40 CSBs in scope. | Production migration active in 2025 | Some boards were at risk of missing individual timelines; final per-board completion is not published. |
| Multiple EHR vendors | Source-system integrations for CSB data. | Go-live handling confirmed | Public material does not list every vendor or final interface state. |
| Master Patient Index | Identify a unique individual across services. | Programme scope confirmed | Detailed matching model and production metrics are not public. |
| Existing reports | Refactored to use the new EDW. | Required scope | Complete inventory and retirement of old reports are not disclosed. |
| Near-real-time ingestion | Improve source-to-warehouse timeliness. | Design objective | Per-source latency and production coverage are not published. |
| CCS3, EDCC/SmartChart, Millennium EHR | Related systems and potential data-exchange scope. | Related programme context | Exact cutover status of each named system is not uniformly documented. |
| Predecessor SQL Server warehouse | Legacy analytical platform to be replaced. | Retirement unconfirmed | No explicit decommissioning date was found. |
Implementation challenge
The May 2025 status report recorded issues as different CSBs went live with different EHR vendors. The programme remained green, and the team reported resolving issues quickly, but the evidence shows that source-system variation—not only warehouse technology—was a material delivery constraint.
Destination architecture and governance
- Core platform: Snowflake Data Cloud.
- Cloud environment: AWS environment supplied by VITA.
- Pattern: serverless, event-driven architecture integrating AWS services with Snowflake.
- Implementation partner: Deloitte, with the contract beginning in July 2024.
- Data model scope: master patient index, new and existing source connections and refactored reporting.
- Reported economics: $11,081,064 total project cost, comprising general-fund and non-general-fund sources.
Completion semantics
The December 2025 status report establishes that the final release was implemented. The May 2026 portfolio status establishes project completion. Those facts do not by themselves establish that every legacy SQL Server component, report or interface was switched off in May 2026.
Known unknowns and monitoring questions
- The exact date of SQL Server warehouse decommissioning.
- Whether every one of the 40 CSBs completed migration on its original timetable.
- The current operating status and service performance of the Snowflake platform after project closeout.
- The Snowflake edition, region and full resilience configuration.
- The final production status of every related source system and interface.
- Whether all predecessor reporting assets were retired or retained for historical use.
PlatformTrace analysis
The strongest evidence supports a completed modern-data-platform programme with production workloads moving during 2025 and the final release delivered by December. The May 2026 “complete” designation is best interpreted as portfolio and administrative closure, not the technical cutover date.
For enterprise clients, the useful lesson is that the warehouse replacement depended on a federated source estate: 40 boards, multiple EHR vendors, identity resolution and report refactoring. The difficult part was not simply provisioning Snowflake. It was aligning heterogeneous operational systems and moving each producer into a governed data model.
Next monitoring triggers
- An explicit predecessor-retirement notice.
- Post-implementation performance or adoption reporting.
- Expansion to additional data sources.
- Public confirmation that all 40 CSBs completed migration.
- Any follow-on procurement for the same platform.
Evidence ledger
- DBHDS FY24–26 IT strategic planOfficial agency plan · 30 November 2023 · proves project start, predecessor-replacement objective, original schedule, report refactoring and ingestion goals.
- Virginia Executive Data Board materialOfficial governance material · August 2024 · proves AWS and Snowflake development-environment preparation.
- VITA May 2025 project status reportOfficial status report · May 2025 · proves CSB production go-lives, EHR-vendor issues and continuing migration work.
- VITA December 2025 project status reportOfficial status report · December 2025 · proves the final release and planned closeout.
- DBHDS FY26–28 IT strategic planOfficial agency plan · 7 October 2025 · proves Deloitte, AWS hosting, replacement framing and MPI scope.
- VITA May 2026 major-project portfolioOfficial portfolio · May 2026 · proves completed-project status and programme economics.
- AWS re:Invent 2025 DBHDS and Deloitte sessionTechnical conference presentation · December 2025 · supports Snowflake-on-AWS and serverless event-driven architecture.
Corrections and update history
- Initial verified record published with production and completion boundaries.
- Expanded into a dossier covering project chronology, economics, architecture, CSB/EHR scope, MPI work and the unconfirmed predecessor-retirement boundary.
No correction is currently open. Explicit retirement or later operating milestones will be appended.